Early Flood Warning
LMCC REQUIRED AN EARLY FLOOD WARNING SYSTEM ON WEIR ROAD
Location: Weir Road, Lake Macquarie City Council
Client: LAKE MACQUARIE CITY COUNCIL
Early Flood Warning
Weir Road is a 6 km road linking Teralba and Barnsley in the Lake Macquarie City Council area. It is predominantly low level and prone to frequent flooding.
During periods of flooding Lake Macquarie City Council crews would need to go to both the Teralba and Barnsley ends of Weir Road and close the road off to motorists, stopping direct traffic through the area.
To warn motorists of the imminent danger of flooding an early flood warning system was developed by Hi-Vis Group which operated as follows:
- Water level sensors were placed along Weir Road at a level below flood points
- During periods of heavy rain, as Lake Macquarie rose in level, usually accompanied with a high tide, the sensors would activate
- Once activated, the sensors would automatically message [via SMS] nominated LMCC personnel
- LMCC personnel would then activate a group of 5 warning signs spread along Weir Road near both entrances
- These warning signs incorporated dual flashing lights [wig wams] that warned approaching motorists of the flooded road and not to enter
This system was effectively designed and deployed as a 24/7 first response to warn motorists of impending anger of the flooded road until such time LMCC crews arrived to close the road access entirely.
Have a Project you'd like to Collaborate on?
Send us a message and we'll be in touch to discuss how we can work together.
More Projects
View all-
Inner West Council Speed Limit Rollout
Rapid Signage Delivery for Inner West Council Speed Limit Rollout Project Overview In June 2026, HIVIS delivered a large-scale signage supply program for Inner West Council, supporting the rollout of...
Inner West Council Speed Limit Rollout
Rapid Signage Delivery for Inner West Council Speed Limit Rollout Project Overview In June 2026, HIVIS delivered a large-scale signage supply program for Inner West Council, supporting the rollout of...
-
On the Fast Track
When Sydney Trains needed to prepare its iconic XPT Trailer Cars for a major milestone, their 40-year anniversary event, they faced a classic asset management dilemma. The fleet required a...
On the Fast Track
When Sydney Trains needed to prepare its iconic XPT Trailer Cars for a major milestone, their 40-year anniversary event, they faced a classic asset management dilemma. The fleet required a...
-
Building the next generation of School Zone Alerts
When public safety infrastructure ages, the challenge is not simply replacement. It is modernisation without disruption, and innovation without loss of trust. Through the NSW Government Small Business Innovation and...
Building the next generation of School Zone Alerts
When public safety infrastructure ages, the challenge is not simply replacement. It is modernisation without disruption, and innovation without loss of trust. Through the NSW Government Small Business Innovation and...